Get Ready For a Very Uncomfortable Year on the Brooklyn Bridge

There’s crowded, and then there’s the Brooklyn Bridge on a nice warm day with construction fencing off half the walking and biking path. Image: DOT

Just as the weather warms and tourists once again mob the Brooklyn Bridge to admire the skyline and snap some photos, DOT has announced that construction work will narrow the one place on the bridge path that’s even remotely close to comfortably wide.

The maintenance work involves “steel improvements at tower locations as well as structural joint repair on the Brooklyn approach.” For people walking and biking on the bridge path, that will mean squeezing around construction fences blocking off one side of each tower.

Nowhere to pause for photos, nowhere to not be in the way of other people. Image: DOT
Image: DOT

During overnight hours, part of the Brooklyn side of the path will also be halved.  The closures, which are more intrusive than previous construction barriers, will be in place through December. Additionally, between April 6 and April 20 DOT will close half the Manhattan approach during overnight hours.

This doesn't work for anybody. Photo: Stephen Miller
This doesn’t work for anybody. Photo: Stephen Miller

Making matters worse, NYPD continues to park its Interceptor vehicles on the bridge path, as it has since the department was embarrassed by a pair of German artists who climbed the bridge towers to install white flags last year.

There’s only one way to make this situation bearable: Convert one of the bridge’s car lanes to a bikeway for the summer and see what happens.

ALSO ON STREETSBLOG

Brooklyn Bridge Promenade Expansion Could Start in 2019

|
An expansion of the Brooklyn Bridge walking and biking path could get underway by 2019 if it’s folded into a rehab project that’s already in the pipeline, DOT Commissioner Polly Trottenberg said this afternoon. The path is as narrow as 10 feet at pinch points and cannot comfortably accommodate the thousands of people who use it each […]

Pulaski Bridge Bike Path Now Scheduled to Open by End of 2015

|
About a year behind schedule, a major project to improve walking and biking between Queens and Brooklyn is set to move forward in 2015. The project, originally scheduled to be complete this year, will convert one southbound car lane on the Pulaski Bridge into a protected bike lane, giving more breathing room to pedestrians on what […]