Brooklyn Waterfront Greenway Coming to Life on West Street

New two-way bike lane markings at West Street and Kent Street in Greenpoint. Photos: David Meyer
New bike lane markings last year on West Street by Kent Street in Greenpoint. Photo: David Meyer

A two-way protected bike lane is taking shape on seven blocks of West Street in Greenpoint, part of a Brooklyn Waterfront Greenway segment that will eventually run 12 blocks between Eagle Street and Quay Street.

The Department of Design and Construction began work on West Street last spring, more than three years after the design was approved by the local community board. The project also includes bioswales and high-level sewers to prevent stormwater from overwhelming the sewage system underneath the street.

Con Edison is digging up the block of West Street between Java Street and India Street.
Con Ed is doing work on the block of West Street between Java Street and India Street.

Today Con Ed crews were digging up West Street between Java and India. North of that block, West Street remains unpaved and is being used partially as a construction staging zone. A spokesperson for DDC told Streetsblog that greenway work is on hold while the agency “[coordinates] with the pier property owners and Con Edison.”

The West Street project is one of 23 segments that will eventually comprise the full 14-mile Brooklyn Waterfront Greenway between Greenpoint and Sunset Park.

No other segments began construction in 2016, according to Brian McCormick of the non-profit Brooklyn Greenway Initiative. But design is complete for two segments — Flushing Avenue along the Brooklyn Navy Yard and Hamilton Avenue in Sunset Park — that are now ready for construction.

DDC says the Flushing Avenue segment will start construction this month. The design was approved by Brooklyn CB 2 in 2013, then was delayed while National Grid relocated a gas main that interfered with construction.

ALSO ON STREETSBLOG

Eyes on the Street: First Signs of Greenway Construction on West Street

|
More than three years after it was approved by Brooklyn Community Board 1’s transportation committee, construction on the West Street segment of the Brooklyn Waterfront Greenway is finally underway. The Department of Design and Construction confirmed that current work on West Street is related to the greenway. The project will turn West Street into a one-way […]

Greenpoint Gets a Preview of Brooklyn Waterfront Greenway on West Street

|
NYC DOT and consultants for the Department of Design and Construction gave Greenpoint residents a glimpse of preliminary designs for the West Street segment of the Brooklyn Waterfront Greenway Wednesday night at a full meeting of Brooklyn Community Board 1. The two-way bikeway proposed for West Street is the first of 23 capital projects that will eventually comprise the finished, 14-mile […]

Brooklyn CB 1 Committee OKs West Street Greenway, Borinquen Place Plans

|
Last night, Brooklyn Community Board 1’s transportation committee voted 3-0 in favor of a preliminary design for the Brooklyn Waterfront Greenway’s first capital project on West Street in Greenpoint, and, in a separate 3-0 vote, endorsed pedestrian safety improvements for Borinquen Place in Williamsburg. These projects will bring major improvements for biking and walking on these two […]

Brooklyn CB1 Approves Bike Path in Place of Parking

|
Here’s how space is divvied up on Kent Avenue today… On Tuesday night, Community Board 1 in north Brooklyn voted 39-2 to support adding a separated bike path to Kent Avenue, a truck route through Williamsburg and Greenpoint. The path will be part of the Brooklyn Greenway, which is slated to follow the waterfront from […]