Lentol: Pulaski Bridge Bikeway Construction to Begin September 14
Construction of the Pulaski Bridge protected bike lane is now set to begin in a matter of days, according to Assembly Member Joe Lentol, and could wrap before the end of the year.
DOT had announced last month that drainage design issues would delay the start of construction until next March, but that no longer seems to be the case.
Lentol says the complications have been resolved sooner than expected, and DOT will begin installation of the bikeway on September 14, potentially wrapping up by the end of the year.
DOT did not respond to an inquiry about the project timeline.
The Pulaski Bridge bikeway will provide relief for pedestrians and cyclists who currently share a narrow path on the west side of the bridge between Greenpoint and Long Island City. It will also calm traffic on the southbound side the bridge, which funnels traffic onto McGuinness Boulevard in Greenpoint and will have two lanes instead of three.
The project had already been delayed once after the initial timetable pegged it for completion last year. It looks like there won’t be a second major delay after all.
With Citi Bike arriving on both sides of the bridge this month, that’s welcome news to Lentol, who’s been a booster of the project since 2012. “I am delighted that this project could potentially be completed before the winter. We have been fighting for a long time for this dedicated bike lane,” he said. “I applaud DOT and the company fabricating the barriers for making this project a top priority.”